This is a point-in-time record of the week of 2026-08-03 to 2026-08-09. It was written from the repository's history for that week and is not revised afterwards, so later pages may supersede what it says.

Week of 2026-08-03 to 2026-08-09

Window: 2026-08-03 00:00:00 to 2026-08-09 23:59:59, local author time Recapped: 2026-08-21 Commits in window: 1 (1 non-merge, 0 merges)

One commit, on the last working day of the week. It is the week work resumed after a seventeen-day break — the maintainer was on vacation, per their own account on 2026-08-21 — and the commit it resumed with set up everything the following week then measured and rejected.

This recap was written on 2026-08-21, twelve days after its window closed, to fill a gap in docs/recaps/ rather than at the end of the week it describes. Everything below was read from git and from the plan documents on that date.

What shipped

Plan 114 — the sectioner itself, built and gated

8cab72a on 2026-08-08 landed Stages 0-2 of Plan 114: 1,005 lines across processing/html_sections.py and its tests, splitting raw cars.com detail pages into named, content-addressed sections. No MinIO, no scripts, no scraper or production changes.

The plan exists because Plan 110 found that whole-file byte hashes do not match even when parsed vehicle state is unchanged, with the difference concentrated in request, session and analytics regions while the vehicle data stays stable. If sections could be made stable and reusable, artifacts could be retained far longer than a 30-day window — which is the prize the whole audit was chasing.

Three decisions in the commit are worth keeping, because each is a refusal:

The Stage 2 gate passed on all three fixtures. What it did not yet touch is the storage question — whether sectioning is worth doing — which is Stage 3, and Stage 3 ran the following week at 1f0e847 and answered no on a 223% regression. See 2026-08-16.

What moved between states

Nothing. docs/PLANS.md has no revision with an author date inside this window, so no plan entered, left or changed table — including Plan 114, whose implementation this week was.

What is still owed

Unattributed commits

None. The window's single commit names Plan 114 in its subject.

Merges

None. 8cab72a reached master the following week, inside 788bb33 (PR #184) on 2026-08-10, which is counted in 2026-08-16 — the one merge in that window that carried work in from before it.

Deferred to the next recap

173 commits fall after this window's end, as of 2026-08-21.

git rev-list --count --all --since='2026-08-09 23:59:59'   # 173

Because this recap was backfilled, most of that tail is no longer deferred: the week ending 2026-08-16 is recapped. What remains genuinely uncovered is the week of 2026-08-17, which is not complete and so is not recappable yet.